Project Schedule

Construction begins February 4, 2008. The contract is for 400 calendar days after construction begins. The bridge is scheduled to be closed on Monday, September 29, 2008. It will be closed for 45 calendar days. (Please see the detour map on the Traffic Updates page.)

 

Construction Began February 4, 2008
Activities from March - September 2008
Install temporary hydraulics
Install traffic control devices
Replace timber on fender system
Concrete spall repair
Sidewalk removal & replacement on bridge
Restoration of embankments at bridge approaches
Install sidewalk west of bridge on north side of roadway
Bridge Closes September 29, 2008
Activities from Sept 29 - Nov 13, 2008
Bridge steel deck replacement
Recondition structural steel on bridge
Recondition bridge mechanical & electrical operating system
Hydro demolition of concrete approach spans
Restoration of concrete deck
Repair existing piles (pile jackets)

 

     